02 The claim-at-risk meter
How much rides on your notices in a year?
Drag the two bars to match your company. Nothing you set here is sent anywhere.
The rand you would ask for in one claim: extra time costs, extra work, standing time. Start value is an example.
Count across all your sites. Start value is an example.
At risk in a year, if the notices go in late
R4,500,000
One late notice loses one claim: R1,500,000
Your value times your count. It is not a survey figure. Example inputs
Why the whole claim? The JBCC building contract (edition 6.2, June 2024) gives you 20 working days to give notice of a delay claim, failing which the contractor shall forfeit such claim
[1]. Law firm Pinsent Masons calls this a strict time bar [2]. Real cases: in 2012 a High Court held a contractor's time claims forfeited because the contract's notice steps were not followed [4]. In 2022 a contractor sent its notice of dissatisfaction with an adjudicator's award late; the court ordered it to pay R908,047.44 plus costs on the punitive scale [3]. Numbers in brackets point to the sources.
03 Try the tracker
Pick what happened and when. See the deadlines it starts.
An example, built on the standard JBCC contract. Your signed contract can change any of these periods: check your own.
Choose the event. The list below changes to match it.
Starts on today. Pick any date: past dates show how long ago a deadline passed.
Your count runs through December or January. Your contract's recorded builders' holiday does not count as working days. This example does not know your dates, so a real deadline may fall later than shown. Earlier is the safe side.
Working days skip Saturdays, Sundays and South African public holidays [5], as the contract defines them [1]. A holiday that falls on a Sunday moves to the Monday. Example, check your own contract
04 How it works
Three steps. Every clock, as a date.
/01
Send one event
Email what happened, the date, and the contract it falls under. A past claim is fine for your first run.
/02
Get every deadline
We list each notice that event starts, as dates, with who sends it to whom, read off your signed contract.
/03
Get reminded
You get a reminder before each deadline. You write and send every notice yourself.
Your first run is free
Send us one claim you made in the past. We show you every deadline it started and whether each notice went in on time. You keep the result either way.
Not legal advice
We are not attorneys. We read dates off the contract you give us and count. For what a notice should say, or whether a claim is good, ask your attorney.
04b Start here
Send one past claim. See every deadline it started.
It is free. We sign an NDA first if you want one. You keep the result either way.
Opens an email to director@khanandsutra.com with the subject “Free first run”.
Rings the director’s phone.
05 Sources
Every fact on this page, and where to check it.
- [1]JBCC Principal Building Agreement, edition 6.2, June 2024 (reference copy)Working days: page 4. Delay notice, 20 working days, forfeit: page 20 (cl 23.4.2). Full delay claim, 40 working days: page 20 (cl 23.5). Expense and loss notice, 20 working days, forfeit, then claim in 40: page 23 (cl 26.5, 26.6). Principal agent answers in 20, silence is refusal: pages 20 and 23. Notice of dissatisfaction, 10 working days: page 28 (cl 30).
- [2]Pinsent Masons, “South African contractors and employers must ensure understanding of PBA clauses and consequences”, 9 July 2025The delay notice is a strict time bar. The full claim step has no forfeiture words, but a late claim can be refused.
- [3]Tek-cent Glass & Aluminium v Belo & Kies Construction [2022] ZAGPPHC 126, 22 February 2022 (SAFLII)Notice of dissatisfaction given “far more than the stipulated period of ten days” after the award (para 26). Order: pay R908,047.44 and costs on the attorney and own client scale (para 35). Older JBCC subcontract, edition 5.
- [4]Cox Yeates, “JBCC Principal Building Agreement – Clause 29 Extension of Time Claims”, Richard Hoal, 27 August 2012On NV Properties v Radon Projects (Grahamstown High Court, 17 May 2012): time claims that did not follow the notice clause were held forfeited. Older JBCC edition.
- [5]South African Government, Public holidaysThe 12 public holidays under the Public Holidays Act 36 of 1994, and the Sunday-to-Monday rule.